PEACH COUNTY T-SPLOST

UPDATE - SEPTEMBER 2, 2022 T-SPLOST AND SPLOST ROAD RESURFACING

Completed Pavings include:

- Camp John Hope Road

- Norwood Springs Road

- Clopine Lake Road

- North Peach Park

- Kewanee Drive

- West Seminole Drive

- East Seminole Drive

- Rum Road

- Old Hickory Road

铺路后,每条道路将定期进行额外的工作,包括铺路肩, grassing, and permanent striping.

请注意,时间表将根据天气和进度而更改, and will be updated as needed.

感谢您的耐心和理解,因为我们继续这些项目!


UPDATE - AUGUST 12, 2022 T-SPLOST AND SPLOST ROAD RESURFACING

Completed Pavings include:

- Camp John Hope Road

- Norwood Springs Road

- Clopine Lake Road

- North Peach Park

铺路后,每条道路将定期进行额外的工作,包括铺路肩, grassing, and permanent striping. North Peach Park is scheduled to be striped August 15th-19th.

日程将根据天气和进度变化,并将每周更新一次.

感谢您的耐心和理解,因为我们继续这些项目!


UPDATE - AUGUST 5, 2022 T-SPLOST AND SPLOST ROAD RESURFACING

1. Norwood Springs Road - Complete

2. Camp John Hope Road - Complete

3. Clopine Lake Roaq - Currently paving. Projected date of completion is August 8th.

4. North Peach Park - August 9th-10th.

5. Willow Lake Road - August 15th-17th.

6. Park & Industrial - August 18th-19th.

7. Buckeye Road - August 22nd-September 2nd.

请注意,时间表将根据天气和进度而更改,并将每周更新.


UPDATE - JULY 29, 2022 T-SPLOST AND SPLOST ROAD RESURFACING

1. Norwood Springs Road - Complete

2. Camp John Hope Road - Complete

3. Clopine Lake Road - August 1st - August 8th

4. Willow Lake Road - August 9th - August 12th

5. North Peach Park - Earth work is to be completed August 3rd. Paving is projected to be completed August 12th. Striping is scheduled thereafter.

Thank you for your patience as we continue this project. Photos to come!


 

UPDATE - JULY 13, 2022 T-SPLOST AND SPLOST ROAD RESURFACING

One contract for Road Resurfacing Project has been signed, and we are ready to get boots on the ground!  Construction crews will start work at the North Peach Park Parking Lot (SPLOST) this week and early next week.  The following schedule was given to us by the contractor:

  1. Clopine Lake Road (SPLOST) – starting Friday, July 15, most likely July 18
  2. Norwood Springs Road
  3. Camp John Hope Road
  4. Willow Lake Road
  5. South Peach Park & Industrial Road

We will update you as soon as we receive new information. Thank you!


UPDATE - MAY 11, 2022

Bids were opened on May 5, 2022 at 2 p.m.在这一点上,所有的信息都被收集起来供工程公司审查.

On May 9, 2022, 审查委员会开会审查所有提交的投标,以确保所有文件都提交并被接受.

On May 10, 2022, 审查委员会在董事会定期会议期间向董事会提出建议.

委员会接受了审查委员会的建议,并接受了来自Reams和Robinson的投标,重新铺设Peach县的道路.

What follows is the signing of the contracts by the Chairman, which we hope to complete in the next two (2) weeks.

以下是将在T-SPLOST重铺项目的第一阶段完成的道路清单. Further information will be posted as soon it becomes available.

Two (2) companies are completing the resurfacing of the roads, and the work should take six to nine months, weather permitting.

Road Name Length
Clopine Lake Rd 3.25 miles
Preston Rd .04 miles
Lakeview Rd 5.5 miles
North Peach Park Parking Lot Phase 1  
Taylors Mill Rd Phase 1 .03 miles
Buckeye Rd Phase 1-5 7.16 miles
Camp John Hope Phase 1 1.4 miles
Carver Dr.  1.4 miles
Industrial Blvd/S Park Rd loop .5 miles
Knoxville St.  .25 miles
Mathews Rd .65 miles
Norwood Springs Rd 3.1 miles
Woolfolk Rd 2.25 miles
Lane Rd .05 miles
Taylors Mill Rd Phase 2 3.25 miles
E. Seminole 1.25 miles
Willow Lake Rd 1.75 miles
Old Hickory Rd .75 miles
Old Oak Rd .55 miles
Red Oak Rd .60 miles
Rum Rd/Main Street 1.4 miles
West Seminole Loop 1.05 miles
Hartley Rd 1.25 miles
State University Dr 2.5 miles
Sylvan Dell Rd .05 miles
Roger Dr .06 miles
Sherwood Blvd .65 miles
Sudan Rd .55 miles
Fort Drive .02 miles
Peach Rd .63 miles
Valley Rd .63 miles
Fieldcrest Rd .65 miles
Powersville Rd Phase 1 2.5 miles
River Rd 6.75 miles
Champagne Dr.  .03 miles
Housers Mill Rd 1.2 miles
Sledge Rd .62 miles
Jones Rd 1.45 miles
Kay Rd 1.65 miles
Bible Camp Rd 2.4 miles
Burnette Rd 3.15 miles
E. Wesley Chapel Rd 1.1 miles
Hedgerow Circle .65 miles
W. Wesley Chapel Rd 1.1 miles
Moseley Rd 7.2 miles

 

 

自从桃子县的选民批准了T-SPLOST和债券发行11月2日, 2022, 桃县委员会一直在与债券顾问合作,以完成债券发行.  The estimated completion date is March 30, 2022.  At the same time, 委员会一直在与两个工程小组合作,设计重新铺设被列为主要道路的大多数道路.   工程组已经完成了他们的工作,我们将在2022年3月23日进行投标.  投标名单将在当地报纸(《新皇冠现金官方》)和我们的网站上公布.  We have to run those ads for 30 days.  

We will update further as we progress. Thank you!


整个桃县的交通系统是唯一最重要和最昂贵的基础设施系统的建设和维护. 我们的县道和城市街道每天都被旅行的公众使用. 这个交通系统的建设和维护对我们社区居民的生活质量至关重要, and its attractiveness to industry and commerce.

The residents of Peach County, 包括那些住在拜伦市和谷堡市的人, 是否可以利用单县运输特殊用途地方选择销售税(T-SPLOST)来解决多种运输问题. From paving and resurfacing numerous streets in the City of Byron, City of Fort Valley, and the unincorporated area of Peach County. 这项倡议所筹集的资金百分之百将用于这个社区的交通项目.

Peach County Chairman Martin Moseley, Mayor Michael Chidester, 和市长芭芭拉·威廉姆斯签署了一项政府间协议,为运输目的的特殊目的地方选择销售税在选民面前扫清了障碍. On June 8, 桃县委员会于11月2日正式召开会议,呼吁将这一项目列入黑名单, 2021, ballot.

所有桃区选民都将考虑征收1美分的销售税,这将为街道和道路等交通项目提供资金, overpasses, traffic control improvements, and more. 这项为期5年的T-SPLOST的收益预计最高为2700万美元. 桃子县,拜伦市和福特谷已经同意与62.93% (Peach County) 16.76% (City of Byron), 17.23% (City of Fort Valley) 1.89% (City of Warner Robins), 1.19%(佩里市)拆分和选择对每个辖区重要的项目.

This website provides information about the T-SPLOST initiative, 包括对使这一倡议成为可能的立法的概述, 一份潜在项目的清单,这些项目将由这个倡议和更多的项目资助.

CLICK EACH IMAGE FOR A PRINTABLE PDF

 

 

TRANSPORTATION SPECIAL PURPOSE SALES TAX

2010年立法机关通过的《皇冠现金网官网》(TIA)为乔治亚州各地提供了一个机会,可以征收1%的区域交通特殊用途地方选择销售税(TSPLOST),以资助本地区的交通改善.

To provide another transportation funding option, the Georgia General Assembly passed a Single County TSPLOST in 2015. 单一县TSPLOST允许不属于区域努力的单个县征收专门用于运输目的的销售税.

要获得单一县tplost的资格,该县必须已经实施了常规的SPLOST. TSPLOST旨在满足超出常规SPLOST的运输需求,或将常规SPLOST腾出用于与运输无关的基本建设项目. 单个县的TSPLOST可以征收长达五年的分数税率高达1% .如果与县内符合条件的城市有政府间协议,则增加0.05%.

如果没有政府间协议,税收只能征收到 .75 percent. With no intergovernmental agreement in place, 县和市之间的默认分配公式是基于最近三个财政年度的交通支出金额的公式.

地区TSPLOST允许征收长达10年的税收,25%的资金是自由裁量的资金,将返还给每个地方政府. 通过区域TSPLOST的一个激励因素是本地维护 & 改善补助金(LMIG)的匹配率为10%,而非区域TSPLOST地方政府的匹配率为30%.